โครงการฟื้นฟู นิคมอุตสาหกรรมบางปะอิน CH.Karnchang Public Company Limited Bang-Pa-In Land Development Co.,Ltd. The Industrial Estate Authority of Thailand โครงการฟื้นฟู นิคมอุตสาหกรรมบางปะอิน Report Date : 22 July 2012
Work progress
soil compaction Work progress Main Entrance soil compaction Work progress = 100.00% soil compaction Schedule = 100.00% OVERALL PROJECT Work progress = 67.90% OVERALL PROJECT Schedule= 61.20% Picture 1 Update 22 July 2012 Remark Progress of work 100%
R.C.FLOOD WALL Work progress Main Entrance R.C.FLOOD WALL Work progress = 41.93% R.C.FLOOD WALL Schedule = 34.29% OVERALL PROJECT Work progress = 67.90% OVERALL PROJECT Schedule = 61.20% Picture 2,3 Update 22 July 2012 Key Slab Wall
Pic 1 : Pouring Concrete Retaining Wall at Connection Between Dike Sta
Pic 2: Pouring Concrete Slab and Wall of R. C. Flood Wall Sta Pic 2: Pouring Concrete Slab and Wall of R.C. Flood Wall Sta. 4+000 to 4+500
Pic 3 : Pouring Concrete Slope Protection Sta. 4+000 to 4+500